Update 06 - Dated 28 February 2017
Dear Valued Customers
This is to inform to you that, containers for discharge port Nhava Sheva are discharged.
You are requested to proceed for clearance, ICD bounded containers will be moved thru rail / road and customers are requested to contact respective agent’s offices for delivery order release.
Nhava Sheva - IGM No - 2158910 Dated : 25th February 2017
eom
Update 05 - Dated 24 February 2017
Dear Valued Customers,
Further to the previous update on 17th February 2017, please be advised that the containers discharged at Colombo are loaded on board of Ikaria as planned.
Her tentative schedule as follows.
Port ETA
Nhava Sheva FEB-26-2017
Pipavav FEB-28-2017
We thank you for your patience and regret the inconvenience caused.
eom
Update 04 - Dated 17 February 2017
Dear Valued Customer,
Further to the previous update on 14th February 2017, it is reported by the vessel operator that vessel CAP Arnauti will berth Colombo on Feb 19th to discharge all containers on board.
The containers destined for India are expected to be loaded on vessel Ikaria Voyage 701 ETD Colombo Feb.23rd.
Her tentative schedule as follows.
Port ETA
Nhava Sheva FEB-26-2017
Pipavav FEB-28-2017
We thank you for your patience and regret the inconvenience caused.
Fourth Notice for Engine breakdown of CIX3 Cap Arnauti Voyage W701
eom
Update 03 - Dated 14 February 2017
Dear Valued Customer,
Further update on Vessel Delay - M.V.CAP ARNAUTI VOY - 701E
Repairs are continuing to CAP Arnauti at ECT Terminal at Colombo port and completion date is not yet confirmed.
The earliest expected berth they are currently being offered at Colombo is Saturday 18th February.
We hope to share more specific news in next round.
Third Notice for Engine breakdown of CIX3 Cap Arnauti Voyage W701
eom
Update 02 - Dated 08 February 2017
Dear Valued Customer,
Refer to the previous notice on 02 February 2017, please be advised that the vessel Cap Arnauti arrived at Colombo under tow on February 7 however berthing is not confirmed yet.
We will keep you update if any news regarding the cargo arrangement and revised vessel schedule.
Second Notice for Engine breakdown of CIX3 Cap Arnauti Voyage W701
eom
Update 01 - Dated 02 February 2017
Dear Valued Customer,
Reference to our below advisory,
Please be informed that M.V.CAP ARNAUTI VOY - 701E have been suffering main engine problem in Indian Ocean.
She will be towed to Colombo for investigation and repairment. (ETA Colombo 8th Feb afternoon, subject to weather, tug & tow speed)
We will keep you update if there is any news regarding the schedule and cargo arrangement.
Preliminary Notice for Engine breakdown of CIX3 Cap Arnauti Voyage W701
eom.
Dated : 30 January 2017
Dear Valued Customer,
As per the information received from vessel operator M.V.CAP ARNAUTI VOY - 701E is delayed due to main engine problem.
Original ETA @ Nhava Sheva : 29th Jan 2017
Revised Tentative ETA @ Nhava Sheva : 02nd Feb 2017
eom