Top
Local Information
Home  /  Local Information  /  
Demurrage & Detention Free Time and Charges
Demurrage & Detention Free Time and Charges
Please use the webpage link to Tariff & Rate Enquiry for full price for your shipment.
All Surcharge and Fees shown are maximum rates and valid until further notice (unless specified).


 

*** wef Sept. 1st 2016 for all non-regulated trades/ wef Sept. 9th for regulated trade *

Export

 

Container detention

-          Freetime: 7 calendar days

-          Milestone: start on the first calendar day after empty pick up from depot, end with laden delivered at the terminal

 

Cargo nature                                    Chargeable days             Currency             Rate per day                                    

Dry cargo                                            From day 1- 3 days         Nok                       Nok 350/20’, Nok 500/40’

                                                               >= 4 days                        Nok                       Nok 550/20’, Nok 700/40’

 

Dangerous cargo                             From day 1 – 3 days       Nok                       Nok 350/20’, Nok 500/40’

                                                               >= 4 days                      Nok                       Nok 550/20’, Nok 700/40’

 

Special equipment                         From day 1 – 3 days       Nok                       Nok 350/20’, Nok 500/40’

(excl. reefer containers)              >= 4 days                            Nok                       Nok 550/20’, Nok 700/40’

 

Reefer containers                          From day 1 – 3 days       Nok                       Nok 750/20’, Nok 900/40’

                                                               >= 4 days                     Nok                       Nok 1100/20’, Nok 1400/40’

 

Container demurrage

-          Freetime: 5 calendar days

-          Milestone: start on the first working day after laden delivered at the terminal, end with loaded onboard feeder

 

Cargo nature                                    Chargeable days             Currency             Rate per day                                    

Dry cargo                                            From day 1- 7 days         Nok                       Nok 450/20’, Nok 600/40’

                                                               >= 8 days                         Nok                       Nok 550/20’, Nok 850/40’

 

Dangerous cargo                             From day 1 – 7 days       Nok                       Nok 450/20’, Nok 600/40’

                                                               >= 8 days                       Nok                       Nok 550/20’, Nok 850/40’

 

Special equipment                         From day 1 – 7 days       Nok                       Nok 450/20’, Nok 600/40’

(excl. reefer containers)              >= 8 days                            Nok                       Nok 550/20’, Nok 850/40’

 

Reefer containers                          From day 1 – 7 days       Nok                       Nok 800/20’, Nok 1100/40’

                                                               >= 8 days                     Nok                       Nok 1150/20’, Nok 1600/40’

 

Import

Container detention

-          Freetime: 7 calendar days

-          Milestone: start on the first working day after laden pick up from terminal, end with empty delivered at the depot

 

Cargo nature                                    Chargeable days             Currency             Rate per day                                    

Dry cargo                                            From day 1- 3 days         Nok                       Nok 350/20’, Nok 500/40’

                                                               >= 4 days                         Nok                       Nok 550/20’, Nok 700/40’

 

Dangerous cargo                             From day 1 – 3 days       Nok                       Nok 350/20’, Nok 500/40’

                                                               >= 4 days                       Nok                       Nok 550/20’, Nok 700/40’

 

Special equipment                         From day 1 – 3 days       Nok                       Nok 350/20’, Nok 500/40’

(excl. reefer containers)              >= 4 days                            Nok                       Nok 550/20’, Nok 700/40’

 

Reefer containers                          From day 1 – 3 days       Nok                       Nok 750/20’, Nok 900/40’

                                                               >= 4 days                     Nok                       Nok 1100/20’, Nok 1400/40’

 

Container demurrage

-          Freetime: 5 calendar days

-          Milestone: start on the first working day after laden arrived at the terminal per feeder, end with laden collected at the terminal

 

Cargo nature                                    Chargeable days             Currency             Rate per day                                    

Dry cargo                                            From day 1- 7 days         Nok                       Nok 450/20’, Nok 600/40’

                                                               >= 8 days                         Nok                       Nok 550/20’, Nok 850/40’

 

Dangerous cargo                             From day 1 – 7 days       Nok                       Nok 450/20’, Nok 600/40’

                                                               >= 8 days                      Nok                       Nok 550/20’, Nok 850/40’

 

Special equipment                         From day 1 – 7 days       Nok                       Nok 450/20’, Nok 600/40’

(excl. reefer containers)              >= 8 days                            Nok                       Nok 550/20’, Nok 850/40’

 

Reefer containers                          From day 1 – 7 days       Nok                       Nok 800/20’, Nok 1100/40’

                                                               >= 8 days                     Nok                       Nok 1150/20’, Nok 1600/40’

 

 

 